Robert H. Lurie Medical Research Center
Project Status
- Demolition started July 9, 2001.
- Demolition completed January, 2002.
- Construction started March 21, 2002.
- Base building construction completion: March, 2005
- 6th Floor build-out completed January, 2006
- 8th Floor build-out completed January, 2006
- 9th Floor build-out started October, 2006
- 10th Floor build-out started August, 2006
Project Description & Statistics
The building site is bound by Fairbanks Court, Superior Street, Huron Street, and Prentice Women's Hospital.
12-story building, approximately 250 feet tall and 40 feet below grade
9 laboratory floors with offices
2 mechanical floors at 2nd floor and penthouse
1 ground floor campus center and service area
2 floors below grade for Vivarium and mechanical rooms
Ground Floor:
Dining for 120 people
Auditorium for 255 people
Auditorium for 111 people
Seminar Room for 75 people
Seminar Room for 45 people
Typical Floor:
12 lab planning modules to accommodate 12 PI's and 5 researchers per PI
75 people per floor with administration
Building Population:
Approximately 700 persons total (PI's, researchers, staff)
| Gross sq. ft. | Net sq. ft. | Net-to-Gross Ratio | |
| Sub Basement |
52,890 |
30,730 |
58.40% |
| Basement |
30,814 |
30,814 |
58.15% |
| Ground Fooor |
25,374 |
25,374 |
56.33% |
| Mezzanine |
2,957 |
2,351 |
79.51% |
| 2nd Floor (Mechanical) |
25,890 |
N/A |
N/A |
| Typical Lab |
24,500 |
14,500 |
59.18% |
| Mechanical Penthouse |
7,647 |
N/A |
N/A |
| Total |
407,921 |
219,769 |
53.88% |
Project Cost: ~$165,000,000 (base building)
Project Team
Project Management:
Ron Nayler, Associate Vice President for Facilities Management
Bonnie Humphrey, Director Facilities Management Design & Construction
John Brzezinski, Senior Project Manager
Jo Le Mieux-Murphy, Projects Administrator
Kory Burton, Project Manager
Jay Seay, Project Engineer
Architect, Engineers & Consultants:
Davis Brody Bond, LLP (New York, NY), Lead Architect
BR+A (Boston, MA), Engineer
Christopher P. Stefanos Associates (Oak Lawn, IL), Structural Engineer
Terra Engineers (Chicago, IL), Civil Engineer
Joseph Carr & Associates (Chicago, IL), Landscaping Design
AMEC (Chicago, IL), Construction Consultant
Horvath-Reich CDC, Inc., Exterior Wall Consultant
Ralph G. Moore and Associates (Chicago, IL), Supplier Diversity Consultant
E Cube, Inc. (Boulder, CO), Commissioning
Shen Milsom Wilke, Inc. (Chicago, IL), audio-visual consultants
General Contractor:
Turner Construction Company
Contact Information
All questions or complaints should be directed to:
John Brzezinski, Senior Project Manager
Northwestern University
Facilities Management Design & Construction
2020 Ridge Avenue, Suite 250
Evanston, IL 60208
Phone: 847-491-3677
Fax: 847-491-3869
j-brzezinski@northwestern.edu