Central Utility Plant - Chilled Water Expansion
Project Status: COMPLETED
Construction Start: August 2007
Completion: Summer 2009
Project Description & Statistics
The Central Utility Plant's chilled water facility shall be expanded approximately 100 feet to the south to accommodate two new 5000 ton chillers. The new chillers provide additional chilled water capacity to accommodate growing chilled water demands from campus development.
Project Team
Project Management
Ron
Gary Wojtowicz, Director of Facilities Planning
Bonnie Humphrey, Director of Facilities Design & Construction
Kory Burton, Project Manager
Bruce Jaime
Dan Murphy
Architect, Engineers & Consultants
Affiliated Engineers, Engineer
DeStefano Partners, Architect
Thornton-Tomasetti Group, Structural Engineer
CYLA Design Associates, Landscape Architect
Primera Engineers, Ltd., Civil Engineer
General Contractor
Ragnar Benson Construction
Construction Details/Street Closures
During the project Campus Drive was closed from the Library to the north end of the Central Utility Plant.
Contact Information
All questions or complaints should be directed to:
Kory Burton, Project Manager
Northwestern University
Facilities Design & Construction
2020 Ridge Avenue, Suite 250
Evanston, IL 60208
Phone: 847-491-3677Fax: 847-491-3869
kory@northwestern.edu