Project Team
Project Management
Ron Nayler, Associate Vice President for Facilities Management
Bonnie Humphrey, Director of Facilities Management Design and Construction
Kory Burton, Project Manager
[ Back to top ]
Project Description & Statistics
New synthetic turf soccer and lacrosse field, new bleachers, new field lighting, new intramural field with natural turf and improved drainage, Cook Parking Lot reconfiguration/expansion totalling 700 Parking Spaces.
[ Back to top ]
Project Phasing
Fencing for Phase 1 of this project will begin on June 12th. The lakefront path east of the Intramural Fields will be closed until September this year. Trees will begin to be transplanted to the temporary tree nursery east of North Point.
Fencing for Phase 2 is scheduled to be installed on Monday, June 18th. This will close off the eastern half of Cook Parking lot. The west half of the Cook parking lot and its drive lane will remain open during this phase.
The Existing Soccer and Field Hockey Fields will remain open in these first two phases.
The contractor will be refrained from working during Commencement weekend starting June 15th.
Phases 3 and 4 will begin subsequent to Phases 1 and 2, around September this year.